WHAT WE PROVIDE

Time Impact Analysis (TIA) Services

Solvix International provides Time Impact Analysis (TIA) services for employers, contractors, subcontractors, developers, project managers, contract administrators, and legal teams who need a reliable prospective assessment of how a specific delay event affects the current accepted programme. A well-prepared TIA helps decision-makers understand whether an event shifted the forecast completion date, affected sectional completion, or changed available float and milestone positions.
Our approach is practical, transparent, and dispute-aware. We review the programme update closest to the event, test the relevant facts and records, build a logical fragnet or impact model, run the impacted schedule, and explain the results in plain language. The aim is not merely to generate a software output, but to provide a defensible analysis that can support project administration, EOT submissions, determinations, negotiation, expert review, or formal proceedings.
SERVICE SCOPE

What our TIA service covers

Typical TIA Events

TIME IMPACT
ANALYSIS
Late design information
Variations and instructed change
Late access or possession
Approval and authority delays
Suspension of work
Employer-supplied items
REPORT OBJECTIVES

What a well-prepared TIA should achieve

A TIA can be prepared contemporaneously during the project to support an EOT request, or reviewed later as part of an EOT determination or dispute. In either case it should be transparent and reproducible.

0 +

Successfully Completed Projects

0 +

Years of Industry Experience

0 M+

Total Project Investment Value

METHODOLOGY

How we perform a Time Impact Analysis

A credible TIA depends on using the right update, modelling the event realistically, and explaining why the inserted impact is reasonable. We do not rely on generic software outputs in isolation. Instead, we combine schedule mechanics, project records, and contractual context so the result is understandable and robust.

Time impact analysis workflow

A disciplined prospective method for evaluating delay events against the current accepted schedule

1. Confirm the baseline for analysis

Identify the relevant accepted programme update, status date, calendars, critical path, and programme assumptions.

➜

2. Define the event and records

Review instructions, notices, RFIs, design releases, procurement issues, access constraints, and event chronology.

➜

3. Build the fragnet or impact logic

Model the delay event using realistic relationships, durations, constraints, and resource-driven sequencing where justified.

4. Insert and run the impacted programme

Integrate the fragnet into the update closest to the event and measure the effect on completion, milestones, and float.

➜

5. Interpret results and entitlement

Evaluate whether the event affected the critical path, concurrent issues, excusable delay, and extension implications.

➜

6. Report clearly and defensibly

Issue a transparent narrative, schedules, assumptions, and outputs suitable for project teams and dispute forums.

We also explain the assumptions behind the selected update, fragnet structure, progress status, and any limitations in the available records. That transparency is important because many TIA disputes turn not on software operation, but on whether the model reasonably reflects the real event and the accepted programme at the time.

WHAT A STRONG EXPERT REPORT INCLUDES

Core elements usually expected in independent construction expert reporting

Issue Framing

Define the question, scope, and assumptions.

Evidence Trail

Show the records and data relied upon.

Methodology

Explain how the analysis was performed.

Findings

Set out the material results and observations.

Opinion

State the conclusion clearly and independently.

INPUTS AND OUTPUTS

Common issues we test in a TIA

Most challenges to a TIA concern a small number of modelling choices. We check each of them when preparing or reviewing an analysis.

1. Update selection:

confirm the update used reflects progress immediately before the event.

2. Progress data:

check actual dates and remaining durations in the update are reliable.

3. Fragnet logic:

test whether the event logic and durations are supported by the records.

4. Concurrency:

identify contractor delays affecting the same path in the same period.

5. Mitigation and float:

consider available float, resequencing, and mitigation actually taken.

RECORDS AND OUTPUTS

Records typically reviewed and deliverables produced

Where appropriate, Solvix can also coordinate TIA findings with wider delay analysis, EOT assessment, disruption review, contractual entitlement review, and quantum support so clients receive one coherent position rather than isolated technical outputs.

Records typically reviewed

  • Accepted baseline and periodic update schedules
  • Progress updates, status dates, progress narratives, and programme revisions
  • Instructions, design releases, approvals, RFIs, and correspondence
  • Notices, claim submissions, meeting minutes, and change logs
  • Milestone commitments, sectional completion dates, and contractual dates
  • Relevant cost, resource, or procurement data where it influences sequencing

Typical deliverables

  • Time Impact Analysis report with executive summary and methodology note
  • Fragnet or impacted programme extract
  • Before-and-after milestone and completion comparison
  • Explanation of critical path movement and float effects
  • Commentary on assumptions, limitations, and concurrency observations
  • Appendices suitable for EOT claims, determinations, negotiation, or expert review
FAQS

Frequently asked questions

A TIA is a prospective delay analysis method used to test how a specific event affects the current accepted programme by inserting a fragnet or impact model into the schedule update closest to the event.

It is commonly used for extension of time assessments, live project claim administration, responses to submitted EOT claims, and contemporaneous decision-making before a dispute matures.

No. TIA addresses the schedule effect of an event. Contractual entitlement still depends on the wording of the contract, notice compliance, causation, concurrency issues, and other project facts.

Yes. We can review the selected update, fragnet logic, assumptions, status data, and interpretation used by another party, then identify strengths, weaknesses, and alternative views.

Yes. TIA often forms part of a wider package that may include EOT assessment, forensic schedule analysis, claims support, expert reports, or arbitration and litigation support.

TIA is usually prospective and contemporaneous, testing the expected impact of a live event on the current programme. Forensic schedule analysis is often retrospective and is commonly used after events have unfolded.

Yes. A well-explained TIA can help parties narrow disagreements about schedule impact, milestone movement, and the scale of time relief before matters proceed to more formal dispute stages.

Our Portfolio

Related Projects

Successfully executed across the globe — showcasing our commitment to excellence.
Cairo Office
Services Available
Local Expertise. Global Standards.
Our Cairo team combines deep local knowledge with international best practices to deliver exceptional results for every project.
UAE Office
Services Available

Local Expertise. Global Standards.

Our Dubai team combines deep local knowledge with international best practices to deliver exceptional results for every project.

KSA Office
Services Available
Local Expertise. Global Standards.
Our Riyadh team combines deep local knowledge with international best practices to deliver exceptional results for every project.
Australia Office
Services Available
Local Expertise. Global Standards.
Our Sydney team combines deep local knowledge with international best practices to deliver exceptional results for every project.
USA Office
Services Available

Local Expertise. Global Standards.
Our US team combines deep local knowledge with international best practices to deliver exceptional results for every project.
UK Office
Services Available
Local Expertise. Global Standards.
Our London team combines deep local knowledge with international best practices to deliver exceptional results for every project.