In brief: Under AS 4000 and AS 2124, a contractor must notify the Superintendent promptly of a possible delay and then submit a written claim within 28 days to be entitled to an extension of time. The Superintendent assesses the claim and also has a separate power to extend time on its own initiative. Most disputes turn on the time bar and on how the principal has amended the general conditions.

The two contracts

AS 2124-1992 and AS 4000-1997 are the Australian Standard general conditions for construct-only work. Both are still widely used on building and civil projects in Australia, usually with extensive special conditions. A proposed replacement, AS 11000, was released as a draft in 2015 but was not proceeded with.

In AS 4000, time and progress are dealt with in clause 34. In AS 2124, the extension of time provisions are in clause 35, with the claim mechanism in clause 35.5. The structure of the two is similar, but the wording is not the same. Always work from the contract you signed, including the Annexure and the special conditions.

Step 1: notify the delay promptly

Both contracts require the contractor to notify the Superintendent in writing when it becomes evident that something may delay the work. The notice must give details of the possible delay and its cause. This is separate from the claim. It is an early warning, and it applies whether or not the contractor thinks it will be entitled to more time.

Under AS 4000 the notice is to be given promptly. Many special conditions add a fixed period, or require the notice to be in a set form. Diary these periods for every potential delay event.

Step 2: the claim within 28 days

Under clause 34.3 of AS 4000, the contractor is entitled to an extension of time for practical completion if it is or will be delayed in reaching practical completion by a qualifying cause of delay, and it gives the Superintendent a written claim within 28 days after it should reasonably have become aware of that causation occurring. The claim must give the facts of the causation and of the delay, including its extent.

Under clause 35.5 of AS 2124, the claim must be given within 28 days after the delay occurs. There has been argument over when a delay “occurs” for this purpose, particularly for continuing delays. The safe course is to claim within 28 days of the delay first affecting the work and to update the claim as the delay continues.

Principals often shorten the 28 days, sometimes to 10 business days or less, and add requirements for the content of the claim. A claim that misses the contractual period may be time barred. Do not assume a tribunal will excuse it.

Qualifying causes of delay

AS 4000 defines a qualifying cause of delay to include acts, defaults or omissions of the Superintendent, the principal and the principal’s consultants, agents and other contractors. Other events can also be qualifying causes unless the Annexure excludes them. Inclement weather and industrial conditions are commonly limited or excluded.

Check the Annexure before preparing any claim. It may also state the number of days allowed for weather, or exclude delay caused by authorities.

What the claim should contain

  • the event, the date it started and the date the contractor became aware of it;
  • the clause relied on and why the event is a qualifying cause of delay;
  • a delay analysis showing the effect on the date for practical completion, usually a time impact analysis on the current programme;
  • the native programme files, not only PDF prints;
  • the supporting records: site diaries, RFIs, directions, correspondence and photographs;
  • any steps taken to reduce the delay.

Some special conditions add a requirement that the contractor must have taken all reasonable steps to prevent or minimise the delay, or that the delay must affect the critical path. Address these points expressly in the claim.

Step 3: the Superintendent’s assessment

Under clause 34.4 of AS 4000, the Superintendent must give a written direction within 28 days after receiving the claim, stating its assessment of the extension. If it does not grant the full extension claimed, it must give reasons. Check your contract for what happens if the Superintendent does not respond in time. Principals commonly amend this provision.

Clause 34.4 also deals with overlapping causes. Where delay caused by a qualifying cause overlaps with delay from other causes, the Superintendent is to apportion the delay according to the contribution of each cause. This is different from the approach often taken in the UK, where the contractor may get the full period of true concurrency.

The Superintendent must act honestly and fairly when assessing claims, even though it is usually engaged by the principal. If the assessment is not reasoned, ask for reasons in writing.

The Superintendent’s unilateral power

Clause 34.5 of AS 4000 allows the Superintendent to extend the date for practical completion for any reason, even where the contractor is not entitled to an extension or has not claimed one. AS 2124 has a similar power in clause 35.5.

In Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, the New South Wales Court of Appeal held that the Superintendent must exercise this power honestly and fairly, and that it can be exercised for the contractor’s benefit where the contractor has not complied with the claim procedure. Many principals now amend the clause to say the power is for the principal’s benefit only and that the Superintendent has no duty to exercise it. Read the special conditions before relying on this power.

Liquidated damages and delay damages

If practical completion is late and no extension is granted, the principal may recover liquidated damages at the rate in the Annexure. An extension of time moves the date from which liquidated damages run.

AS 4000 also provides for delay damages, which are the extra costs the contractor reasonably incurs for days of extension caused by a compensable cause. These are separate from the extension itself and need their own claim and evidence. The rate or method may be set in the Annexure.

Security of payment

Each Australian state and territory has security of payment legislation. A payment claim that includes delay costs can be taken to adjudication, which is fast. The extension of time entitlement may be decided in that process as a step toward the money claim. A well-prepared extension of time claim made under the contract will help if adjudication follows.

A practical checklist

  1. Read the Annexure and special conditions for notice periods and excluded causes.
  2. Notify the Superintendent in writing as soon as a delay becomes evident.
  3. Submit the claim within the contractual period, usually 28 days.
  4. Include the delay analysis, the native programme and the records.
  5. Update the claim if the delay continues.
  6. Diary the Superintendent’s 28-day assessment period and ask for reasons if the claim is reduced.
  7. Claim delay damages separately where the cause is compensable.

This article is general guidance, not legal advice. The contract, the special conditions and the facts of each project decide the outcome.

Related: Delay analysis methods compared · Concurrent delay explained · Prolongation cost claims

Compare contracts: see our table of EOT notice and claim periods under FIDIC, NEC4, JCT, AS 4000 and AIA.

Need support with this topic?

Solvix prepares extension of time claims and delay analysis for contractors on AS 4000 and AS 2124 projects across Australia. Book a free 30-minute call to talk through your project with us.

Ahmed Elsayed
Ahmed Elsayed
Managing Director

Managing Director of Solvix International. Ahmed leads the firm's delay analysis, construction claims and project controls work, and holds an MSc with a specialism in delay analysis. He has prepared delay analyses, extension of time claims and Primavera P6 programmes for contractors, employers and legal teams on projects across the Middle East, Africa, Europe, North America and Australia.