The 2026 conflict has cut shipping through the Strait of Hormuz. In its weekly overview of 17 October 2026, UK Maritime Trade Operations (UKMTO) put transits at about 70% below pre-conflict levels. Long-lead items for UAE and Saudi projects, such as electrical cable, switchgear and chillers, now arrive later and cost more to bring in.
For contractors, the question is who pays for the lost time and the extra cost. The answer depends on the contract, the governing law and, above all, on what the contractor can prove. This guide sets out how to build a Strait of Hormuz construction delay claim that holds up.
1. Start with the contract, not the news
General regional tension is not a claim. A tribunal will look for three things:
- Entitlement. An event covered by the contract or the law, and notices given on time.
- Causation. Proof that the event delayed the works and, for an extension of time, delayed completion.
- Quantum. The time and cost that follow, supported by records.
Most disruption claims fail on the first two. HKA, citing a review of 316 judgments, reports that only 37% of disruption claims succeeded.
2. Force majeure in UAE construction: does FIDIC Clause 18 apply?
Most private projects in the UAE, and many in Saudi Arabia, use FIDIC 2017 or an amended form of it. Clause 18 replaced the old “force majeure” clause with Exceptional Events.
- What qualifies (18.1). An event beyond the party’s control, which it could not reasonably have provided against before signing, could not reasonably avoid or overcome, and which is not substantially attributable to the other party. War and hostilities, whether war is declared or not, are on the list. That does not make relief automatic: the event must also prevent the party from performing identified obligations. Higher freight or slower delivery on its own is not enough.
- Notice (18.2). Notice must be given within 14 days of becoming aware, or when the party should have become aware, of the event, and it must identify the obligations that are or will be prevented. If notice is late, relief only runs from the date the notice is received. Many Gulf contracts amend this period, so check the Particular Conditions.
- Duty to minimise delay (18.3). Use all reasonable efforts to reduce the delay, and give further notice of the continuing effects every 28 days. Record what you did: alternative routes, other suppliers, resequencing.
- Time and cost (18.4). If the event delays completion, the contractor may be entitled to an extension of time under Sub-Clause 8.5. Cost may also be payable: for war and hostilities (18.1(a)) the event does not need to happen in the Country; for events under 18.1(b) to (e) it does. Cost under FIDIC means costs reasonably incurred, without profit. Neither time nor cost is automatic: causation and the cost actually incurred must be proved.
- Termination (18.5). If the event prevents substantially all the Works in progress for 84 continuous days, or for separate periods totalling more than 140 days, either party may give notice of termination, which takes effect 7 days after receipt. A single late delivery will rarely meet this test.
Other routes to check:
- Sub-Clause 8.5(d): extension of time for unforeseeable shortages of personnel or Goods caused by an epidemic or governmental actions. Identify the specific government restriction. A shipping line’s commercial decision to reroute is not a governmental action.
- Sub-Clause 13.6: adjustment for changes in laws after the Base Date, for example new import or customs restrictions.
- Sub-Clause 13.7: adjustment for changes in cost, but only if the contract includes a schedule of cost indexation. Without it, this Sub-Clause does not apply and escalation sits with the contractor unless another clause helps.
For the full claim procedure, see our FIDIC 2017 EOT claim guide and EOT claims in the UAE.
Sub-Clause 18.2 is not a claim notice. For time or money, the contractor must also follow Sub-Clause 20.2: a Notice of Claim within 28 days of becoming aware of the event, and a fully detailed claim within 84 days of that same date, with the contractual or legal basis and contemporary records. Where the effects continue, interim and final claims follow Sub-Clause 20.2.6.
Assessing a Hormuz-related EOT claim? If you have delayed imported equipment, a notice deadline coming up or disputed prolongation costs, we can review your Primavera P6 programme and records and tell you what delay analysis is needed. Send us your project brief.
3. UAE force majeure and EOT claims under local law
Where the contract is silent or unclear, local law fills the gap.
UAE: the new Civil Transactions Law
Federal Decree-Law No. 25 of 2025 replaced the 1985 Civil Code from 1 June 2026.
- Article 236 (force majeure): if performance becomes impossible, the corresponding obligations end and the contract is rescinded. It now also covers partial impossibility and, in continuing contracts, temporary impossibility, where a party may seek modification of the contract.
- Article 224 (exceptional circumstances): if unforeseen general events make performance excessively onerous and threaten serious loss, the court may reduce the obligation to a reasonable level or rescind the contract. This cannot be excluded by contract.
- Article 829(3) (construction contracts): the court may restore the balance of the contract, including by extending time or adjusting the price.
For contracts signed before 1 June 2026, the old Articles 249 and 273 may still matter. Check the transitional provisions with your lawyer.
Saudi Civil Transactions Law
- Article 97: where extraordinary, unforeseeable events make performance excessively onerous and threaten heavy loss, the affected party may ask to renegotiate. It must keep performing while it does. If talks fail, the court may reduce the obligation.
- Article 110: if performance becomes impossible for a cause beyond the debtor’s control, the obligation ends; partial and temporary impossibility are also addressed.
- Article 471(3): where exceptional general circumstances upset the balance of a construction contract, the court may extend the time, adjust the price or terminate.
- Article 179: the court may reduce agreed compensation, including delay damages, where it is excessive or the obligation was partly performed.
4. EOT claim in Saudi Arabia: government and private projects
First establish whether the project is a private contract or a public one. Saudi government projects are usually governed by the Government Tenders and Procurement Law, its Implementing Regulations and the standard government contract, not FIDIC. These set their own procedure for extending the contract period and waiving delay penalties for reasons beyond the contractor’s control. Do not assume FIDIC notice periods apply.
In both cases, a claim based on shipping disruption must link the late delivery to the programme and show its effect on completion. See our guide to extension of time on Saudi government projects.
5. Prove the delay with the programme
Late delivery only matters if it delayed the works.
- Update the programme to the date the event started, with actual progress.
- Model the event as a fragnet: the original delivery date, the revised date and the activities that depend on it.
- Choose a method that fits the contract and the records. A time impact analysis suits a prospective EOT request using the latest update. A windows analysis or another retrospective method suits periods already completed. Either way, identify the controlling path, the float available and any contractor delay. See our comparison of delay analysis methods.
- Deal with existing delay. If the project was already behind, the tribunal will separate historic delay from new delay. A claim that ignores contractor delay will be cut.
- Show the mitigation. Resequencing, earlier fit-out, local substitutes and alternative routes all count.
Delay to non-critical work may give no extension of time but may still cause disruption cost. Keep the two apart.
6. What cost can be recovered
Where a valid contractual or legal entitlement to payment exists, these heads may be recoverable, subject to proof of causation, reasonableness and mitigation. An extension of time does not by itself give a right to money.
- Prolongation: time-related site overheads, supervision and plant for the extended period. See prolongation cost claims.
- Standing time: plant that could not be off-hired, staff and labour that could not be stood down during a safety stop or a delivery gap.
- Demobilisation and remobilisation, including making the site safe and protecting completed work.
- Disruption: lower productivity on the affected work, measured, for example, with a measured mile.
- Extra logistics: higher freight, land transport, insurance and conflict surcharges, where the contract allows them.
Separate the cost caused by the event from normal escalation, existing inefficiency and cost already recovered elsewhere. Do not count idle plant, site overheads and prolongation twice.
7. Records to start keeping today
- Purchase orders with original and revised delivery dates, and supplier letters giving reasons.
- Shipping documents: bookings, re-routing notices, port and customs dates.
- Weekly programme updates with the affected activities marked.
- Daily site records: labour, plant, idle time and work stopped by safety alerts.
- Copies of every notice, with proof of delivery and dates.
- Quotes and invoices showing freight and material price increases.
8. Practical steps this month
- List every long-lead item still to be delivered and check its route.
- Serve protective notices now, even if the full effect is not known. Diarise the 14-day, 28-day and 84-day deadlines and the 28-day updates.
- Check insurance: standard contractors’ all risks policies usually exclude war.
- Check the supply chain: subcontracts and supply agreements may have different notice periods and governing laws.
- Get an independent programme review before the first detailed claim goes in.
Frequently asked questions
Can a contractor claim an EOT for Strait of Hormuz construction delays?
Possibly. The contractor needs a contractual or legal entitlement and must show that the shipping disruption delayed, or will delay, completion. Supplier letters, delivery records and programme updates are the key evidence.
Is the Hormuz disruption force majeure under UAE construction contracts?
Not automatically. Under FIDIC 2017, Clause 18 applies only where the event meets the Exceptional Event test and prevents performance. The new UAE Civil Transactions Law may give further relief depending on the contract and the facts.
How do I prepare an EOT claim in Saudi Arabia?
Start with the contract and, for public projects, the Government Tenders and Procurement Law. Identify the event, follow the notice and extension procedure, and show the effect on completion with reliable programme updates.
Can contractors recover higher freight and prolongation costs?
It depends on the contract, the governing law and the proven cause. FIDIC 2017 may allow Cost for some Exceptional Events, but each cost head must be justified and supported by records.
How Solvix can help
Need an independent review of a Hormuz-related delay? Send us your project location, contract form, latest Primavera P6 update, affected delivery dates and the notices issued so far. We will review the programme evidence, recommend the right delay analysis method and set out the support needed for an EOT or cost claim.
Submit an EOT claim brief or book a 30-minute consultation.
This article is general information, not legal advice. Solvix provides delay analysis and claims support, not legal opinions. Contract amendments and governing law can change the outcome, so take legal advice on your own contract.